Have a Question?

The icon below will indicate if Matt is available to chat. Click here to learn more.

Join Our Email List

  
Search 3rdWard.org
Community Ads

Elmhurst & Algonquin
847-952-9030
Visit Fuller's Online

Community ads are free!
Click here to learn more
and shop Des Plaines.

« Ward Meeting: Meet Your State Rep | Main | River & Rand Redevelopment Plan »
Wednesday
06Jan2010

Casino Update: Development Schedule

Memo from the Department of Community and Economic Development

The preliminary Planned Unit Development (PUD) materials for the Des Plaines Casino development were received by the Department of Community and Economic Development on January 4th and are currently undergoing staff review. Based upon this submittal, we have laid out the following timeline for the Casino’s regulatory approvals:

(subject to change)
January 25th
- Plan Commission review of Preliminary PUD submittal
January 26th - Community Development Committee review of Preliminary PUD
February 16th - City Council first reading of Preliminary PUD and zoning change
March 1st - Second Reading PUD & estimated date of commencement of demolition
March 15th - Tentative start of construction (site work)
July 30, 2011 - Completion

There are intermediary steps which must be adhered to, of course, and the final engineering and Final PUD submittals would have to follow the Preliminary almost immediately, but it looks as though those elements are already nearly complete and the schedule, while aggressive, is achievable.


PrintView Printer Friendly Version

EmailEmail Article to Friend